The point at which you find out is only a moment and then you move on with life. Either preparing to take the test again or preparing to pay the fees for you PE License.

Doesn't matter when it comes. Only that you are determined that that moment will come.
True, but with another kid on the way in December (#3) I would prefer to get this over with now.
You will be out-numbered...after that all bets are off you might as well keep adding to the brood!!!

although I stopped at 3 mine are all 4 years apart and I will begin my 12 college payments in the fall!!!

 
The point at which you find out is only a moment and then you move on with life. Either preparing to take the test again or preparing to pay the fees for you PE License.

Doesn't matter when it comes. Only that you are determined that that moment will come.
True, but with another kid on the way in December (#3) I would prefer to get this over with now.
You will be out-numbered...after that all bets are off you might as well keep adding to the brood!!!

although I stopped at 3 mine are all 4 years apart and I will begin my 12 college payments in the fall!!!
Top

when #3 come, mine will be 4, 2.5 and noob. so roughly 2 yrs apart

 
Last edited by a moderator:
You have to build 300lf of a 5' high concrete wall that is 1' thick. You use 4' by 8' sheets of plywood to build the forms, how much SF of forms do you need to build the wall.
3300 SF?
Face = 300x5 = 1500

Back = 300x5 = 1500

Ends = 5x1 = 5 (x2)

3010 SF.

The size of the plywood doesn't matter. Just like the cutscore...

 
Last edited by a moderator:
But the original question did not say you couldn't alter them

 