Quick question for anyone who's familiar in resource scheduling...
For anyone who doens't have this problem in front of them, the author asks gives a CPM schedule and asks us to calculate which week will utilize the most resources if every activity starts at the earliest possible time? Author also gives the list of activities and the corresponding resources per activity.
The author adds up the resources per week each of the four weeks during the project, but what I don't get is he only gives credit to each activity once throughout the week.
I.E. his answer is Week 1, in which activities AB (7 resources), BC (5 resources), and BD (16 resources) are implemented, so he calculates week 1 to be 28.
But if you add up the resources every day, throughout the week, instead of just giving credit to those resources once per week, you would get a different answer.... So when it comes to resource scheduling, is the answer always going to be like the author found it here? Or are there instances where you could add up the resources per day throughout that said week?
Sorry if this is confusing, I'd just post the problem although I'm fairly new around here and don't know what the procedure is for copyright, etc...
Thanks.
For anyone who doens't have this problem in front of them, the author asks gives a CPM schedule and asks us to calculate which week will utilize the most resources if every activity starts at the earliest possible time? Author also gives the list of activities and the corresponding resources per activity.
The author adds up the resources per week each of the four weeks during the project, but what I don't get is he only gives credit to each activity once throughout the week.
I.E. his answer is Week 1, in which activities AB (7 resources), BC (5 resources), and BD (16 resources) are implemented, so he calculates week 1 to be 28.
But if you add up the resources every day, throughout the week, instead of just giving credit to those resources once per week, you would get a different answer.... So when it comes to resource scheduling, is the answer always going to be like the author found it here? Or are there instances where you could add up the resources per day throughout that said week?
Sorry if this is confusing, I'd just post the problem although I'm fairly new around here and don't know what the procedure is for copyright, etc...
Thanks.