Search results

Professional Engineer & PE Exam Forum

Help Support Professional Engineer & PE Exam Forum:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.
  1. S

    Construction Depth Reference Manual

    The book is OK as a revision note but there are not too many examples like Ruwan book. The crane section was not properly ccovered in the book. Overall it gives basic knowlege of construction mangement. I would not say it's a coplte waste of $100 for you can always resell the book after use.
  2. S

    Are these books adquate for Civil PE in California

    Yea. I called PPI and was advised that the book will be in their store by Mid-August ready to be shipped out.
  3. S

    Are these books adquate for Civil PE in California

    Has any one used "Construction Depth Reference Manual for the Civil PE Exam (CECN)" by Thomas Korman, PhD, PE, PLS in preparing for the construction module. Did the book help?
  4. S

    To All Taking the Construction Module

    Has any one used "Construction Depth Reference Manual for the Civil PE Exam (CECN)" by Thomas Korman, PhD, PE, PLS in preparing for the construction module. Did the book help?
  5. S

    Any Reviews for Traffic & Highway Engineering by Nicholas J. Garber

    How did you obtain the solution manual? Is the manual for the third or the fourth edition? I have been tring to otain the solution manual. Any advise/assistance will help. Sam
  6. S

    Best transportation handbook to purchase?

    I have the third Edition of Traffic and Highway Engineering by Garber and Hoel. I understand that there is a fourth edition. Folks, do you know whether the tables , formulas ans figures in the third edition is current enough for the PE exam. Anxiously waiting for your thought/advice. Sam
  7. S

    Geotech Problem

    The question asked for total pressure and not for effective pressure. The water water pressure is not considered in this case so the answer is 1280.
  8. S

    Effective Stress in Soil

    The given value for pore water pressure (12psi) is actually 10psi. 12psi is a typo error. The procedure is correct.
  9. S

    Construction specific Practice Problems - good resources in print?

    Are the questions in Rjapkse practice problems comparable with that of NCEES? Can we have your feedback may be it is worth buying
  10. S

    Construction specific Practice Problems - good resources in print?

    The stimating and CPM questions in the book are more closely related to the NCEES sample questions. The information you get about from project management books may refer to construction management process. You may also obtain earn value methods (BWCS, ACWP...). Nothing more, but you need books...
  11. S

    Construction specific Practice Problems - good resources in print?

    You may also want to purchase " All-in-one Breath abd Depth " by Dr Indranil. I hope you take sometime to study 1926 OHSA book and Equipment prduction book by Nunally.
  12. S

    Vertical Curve Question

    I tried to solve the problem, my answer is A. Is that the correct answer
  13. S

    Vertical Curve Question

    Using the Formula, L + 2h/L -2h = (v-G1h/v-G2h)^1/2. My answer is A. Can you guys solve the problem
  14. S

    economics problem

    It's now very clear, Thanks everyone for your contribution
  15. S

    Traffic Volume

    I guess your are right, even from your method. Thanks
  16. S

    Traffic Volume

    Can someone help solve this problem: The average number of tractor (trucks) passing through a point is 1500 trucks per hour lane (tphl). The trucks travel at an average speed of 40mph. If the average truck length (bumper to bumper) is 70ft. What is the distance between the trucks?
  17. S

    economics problem

    Hey if we treat the first 10years of maintenance as P/A, why are we multiplying the 2nd yeras of maintenance by P/F. It is confusing. Can somebody really explain this?
  18. S

    School of PE review course

    If it is allowed, Can you share your note with me
  19. S

    Weighted Unit Cost

    Please find the solution to the problem: UC = (A + 4B + C) / 6 Where UC = Forecast Unit Cost, A = Mininmum Unit cost of previous projects B = Average unit cost of previous projects C = Maximum unit cost of previous projects Total Unit Cost = (7.01 + 6.45 + 7.07 + 7.64 + 7.31 + 7.40 +...