Need your help on NCEES Construction PM problem #532. I have no clue how to use the given talbe to solve this problem. Thank you in advance.
#532
A multistory concrete building is being constructed using two level of shores and forms and two levels of reshores. Construction has been completed through Level 8 as shown in the figure. An analysis has been made to the step shown using the assumption that the shores and reshores are infinitely stiff, the slabs and forces are expressed as a multiple of the typical floor dead load, D. The forms and shores combined weight 0,10D at each level installed, and the reshores weigh 0.05D at each level installed. At the end of the previous oeration shown, there is no worker live load. In the next operation, the forms and shores between Levels 6 and 7 are stripped, lown upward, and stored on top of Level 8 for re-erection. The load of workers imposed on Levels 6 and 8 during this next operation is 0.40D on each. The reshores will be moved from between Levels 4 and 5 tp betweem 6 and 7 in a future operation.
As the operation to move the forms and shores from between Levels 6 and 7 to Level8 is ending, but while the workers are still on the floor at Level 8, the load carried by the floor at Level 7 is most nearly:
a. 1.40D
b. 1.45D
c. 1.65D
d. 1.70D
Shore
Loads
Before
step Loads Carrid by Floor in Multiples of D Shore
Loads
After
Step Before
Step Change During Step After Step 0.0D 1.10D 0.70D 1.50D 1.90D 0.65D 1.25D 0.45D 1.45D
#532
A multistory concrete building is being constructed using two level of shores and forms and two levels of reshores. Construction has been completed through Level 8 as shown in the figure. An analysis has been made to the step shown using the assumption that the shores and reshores are infinitely stiff, the slabs and forces are expressed as a multiple of the typical floor dead load, D. The forms and shores combined weight 0,10D at each level installed, and the reshores weigh 0.05D at each level installed. At the end of the previous oeration shown, there is no worker live load. In the next operation, the forms and shores between Levels 6 and 7 are stripped, lown upward, and stored on top of Level 8 for re-erection. The load of workers imposed on Levels 6 and 8 during this next operation is 0.40D on each. The reshores will be moved from between Levels 4 and 5 tp betweem 6 and 7 in a future operation.
As the operation to move the forms and shores from between Levels 6 and 7 to Level8 is ending, but while the workers are still on the floor at Level 8, the load carried by the floor at Level 7 is most nearly:
a. 1.40D
b. 1.45D
c. 1.65D
d. 1.70D
Shore
Loads
Before
step Loads Carrid by Floor in Multiples of D Shore
Loads
After
Step Before
Step Change During Step After Step 0.0D 1.10D 0.70D 1.50D 1.90D 0.65D 1.25D 0.45D 1.45D