I'm working on a project where the site had to be built up with 4 feet of select fill, compacted to 95% in 8 inch lifts, as the geotechnical report recommended. The perimeter beams are to go 30" into the select fill. The contractor doing my pt foundation is telling me he has never done a foundation where the beams don't go at least 12" into undisturbed soil. That would mean the beam should be 5 ft down, the 4 ft built up plus 1 foot into the ground. I contacted my geotechnical engineer, and he said as long as you compacted it down in lifts, and had it tested, which I did, I should be fine. But my contractor is like no, they are wrong. What are your professional thoughts?