jeb6294
Well-known member
Long story short, they do everything backwards here. They put in the water loop around the base and then put in the perimeter road. The road ended up being wider and higher than the original so several of the fire hydrants are about 1-ft off the EOP and half buried. I am trying to do an estimate for the cost of moving the hydrants back about 2 meters which would get them off the EOP and bring them up to a proper elevation.
The whole contract is a big mess so in the interest of being EXTREMELY conservative I just looked up the cost of a fire hydrant install and subtracted the cost of a hydrant since they are just moving them. Apparently that's not good enough for our friendly native contractor so now I'm going to do a realistic estimate. So, is there any reason they couldn't just yank out the pipe between the valve and the tee and put in a piece that is 2 meters longer reusing everything else? I'll have to check in the morning, but I believe it is HDPE pipe which I'm not as familiar with. If you can't reuse the joints once they've been installed, could they just cut the pipe and insert a 2 meter piece in there, i.e. coupler->2m pipe->coupler?
Thanks for the help.
The whole contract is a big mess so in the interest of being EXTREMELY conservative I just looked up the cost of a fire hydrant install and subtracted the cost of a hydrant since they are just moving them. Apparently that's not good enough for our friendly native contractor so now I'm going to do a realistic estimate. So, is there any reason they couldn't just yank out the pipe between the valve and the tee and put in a piece that is 2 meters longer reusing everything else? I'll have to check in the morning, but I believe it is HDPE pipe which I'm not as familiar with. If you can't reuse the joints once they've been installed, could they just cut the pipe and insert a 2 meter piece in there, i.e. coupler->2m pipe->coupler?
Thanks for the help.