I am weak solving CMP problems. I can figure out Critical Path, but if the question is more advance, I am lost. Can somebody fine the easiest way to explain an earliest or latest start date. I also came across the problems such
The connection matrix shown represents a road transportation network between 6 locations.
node
1 2 3 4 5 6
node 1 0 1 0 0 1 1
2 1 0 1 0 0 1
3 0 1 0 1 1 0
4 0 0 1 0 1 0
5 1 0 −1 1 0 1
6 1 1 0 0 1 0
The total number of arcs in the network is
0
1
2
3 , where they asked to find arc links with specific direction assigned to it.
Solution:
An arc is a link with a specific direction assigned to it. From the following graphical representation of the network, there is one arc.
In the connection matrix, a negative number indicates that the direction of travel from one node to another goes against the direction assigned to that arc. The answer is B
i wasn't able to post an arc, but i don't anderstand this problem
The connection matrix shown represents a road transportation network between 6 locations.
node
1 2 3 4 5 6
node 1 0 1 0 0 1 1
2 1 0 1 0 0 1
3 0 1 0 1 1 0
4 0 0 1 0 1 0
5 1 0 −1 1 0 1
6 1 1 0 0 1 0
The total number of arcs in the network is
0
1
2
3 , where they asked to find arc links with specific direction assigned to it.
Solution:
An arc is a link with a specific direction assigned to it. From the following graphical representation of the network, there is one arc.
In the connection matrix, a negative number indicates that the direction of travel from one node to another goes against the direction assigned to that arc. The answer is B
i wasn't able to post an arc, but i don't anderstand this problem