Construction Afternoon Sample Question #508, Pg. 47 of 2008 Copyright Book
I don't understand how they are getting the solution for Activity G on Pg. 151.
ES = 9
EF = 11
Duration = 2 days
Shouldn't LF = 11 and LS = 9 ?
Where do they get 13 as the LF of Activity G? I think this is an error or maybe they are missing an arrow between activities G and H. I don't see any corrections for this problem in the Errata posted October '08.
I don't understand how they are getting the solution for Activity G on Pg. 151.
ES = 9
EF = 11
Duration = 2 days
Shouldn't LF = 11 and LS = 9 ?
Where do they get 13 as the LF of Activity G? I think this is an error or maybe they are missing an arrow between activities G and H. I don't see any corrections for this problem in the Errata posted October '08.