NTSB DETERMINES INADEQUATE LOAD CAPACITY DUE TO DESIGN

Professional Engineer & PE Exam Forum

Help Support Professional Engineer & PE Exam Forum:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.

csb

Well-known member
Joined
Sep 28, 2007
Messages
9,303
Reaction score
3,088
Location
acquiring satelites...
Washington, DC - The National Transportation Safety Board
has determined the probable cause of the collapse of the I-

35W bridge in Minneapolis, Minnesota, was the inadequate

load capacity, due to a design error by Sverdrup & Parcel

and Associates, Inc., of the gusset plates at the U10 nodes,

which failed under a combination of (1) substantial

increases in the weight of the bridge, which resulted from

previous modifications, and (2) the traffic and concentrated

construction loads on the bridge on the day of the accident.

Contributing to the design error was the failure of Sverdrup

& Parcel's quality control procedures to ensure that the

appropriate main truss gusset plate calculations were

performed for the I-35W bridge and the inadequate design

review by federal and state transportation officials.

Also contributing was the generally accepted practice among

Federal and State transportation officials of giving

inadequate attention to gusset plates during inspections for

conditions of distortion, such as bowing, and of excluding

gusset plates in load rating analysis.

"We believe this thorough investigation should put to rest

any speculation as to the root cause of this terrible

accident and provide a roadmap for improvements to prevent

future tragedies," said NTSB Acting Chairman Mark V.

Rosenker. "We came to this conclusion only through

exhaustive efforts to eliminate each potential area that

might have caused or contributed to this accident.

"Bridge designers, builders, owners, and inspectors will

never look at gusset plates quite the same again, and as a

result, these critical connections in a bridge will receive

the attention they deserve in the design process, in future

inspections, and when bridge load rating analyses are

performed. By addressing all three areas in our

recommendations, we are hopeful that industry and government

bodies will take appropriate action and the American people

can continue to have confidence in the safety of our

nation's bridges," he added.

About 6:05 p.m. Central Daylight Time on Wednesday, August

1, 2007, the eight-lane, 1,907-foot-long I-35W highway

bridge over the Mississippi River in Minneapolis, Minnesota,

experienced a catastrophic failure in the main span of the

deck truss. As a result, 1,000 feet of the deck truss

collapsed, with about 456 feet of the main span falling 108

feet into the 15-foot-deep river. A total of 111 vehicles

were on the portion of the bridge that collapsed. Of these,

17 were recovered from the water. As a result of the bridge

collapse, 13 people died, and 145 people were injured.

During its investigation, the Safety Board learned that 24

under-designed gusset plates, which were about half the

thickness of properly sized gusset plates, escaped discovery

in the original review process and were incorporated into

the design and construction of the bridge.

On the day of the collapse, roadwork was underway on the I-

35W bridge, and four of the eight travel lanes (two outside

lanes northbound and two inside lanes southbound) were

closed to traffic. In the early afternoon, construction

equipment and construction aggregates (sand and gravel for

making concrete) were delivered and positioned in the two

closed inside southbound lanes. The equipment and

aggregates, which were being staged for a concrete pour of

the southbound lanes that was to begin about 7 p.m., were

positioned toward the south end of the center section of the

deck truss portion of the bridge near node U10 and were in

place by about 2:30 p.m.

Shortly after 6 p.m. a lateral instability at the upper end

of the L9/U10W diagonal member led to the subsequent failure

of the U10 node gusset plates on the center portion of the

deck truss. Because the deck truss portion of the I-35W

bridge was considered non-load-path-redundant, the total

collapse of the deck truss was unavoidable once the gusset

plates at the U10 nodes failed.

The NTSB examined other possible collapse scenarios - such

as corrosion damage found on the gusset plates at the L11

nodes and elsewhere, fracture of a floor truss, pre-existing

cracking in the bridge deck truss or approach spans,

temperature effects and shifting of the piers - and found

that none of these played a role in the accident.

As a result of its investigation, the NTSB made nine

recommendations to the Federal Highway Administration and

the American Association of State Highway and Transportation

Officials dealing with improving bridge design review

procedures, bridge inspection procedures, bridge inspection,

training and load rating evaluations.

A synopsis of the Board's report, including the probable

cause, conclusions, and recommendations, is available on the

NTSB's website, www.ntsb.gov, under "Board Meetings." The

Board's full report will be available on the website in

several weeks.

-30-





 
I heard it was because of the caustic effects of bird poop. What do those NTSB guys know?

 
Back
Top