If 224,800 CY of soil are removed froma highway embankment in which the void ration is e=1.22. How many CY of fill having a e=0.78 could be constructed.
The solution is:
e=(Vt/Vs) - 1
solve for Vs = 101,261 CY
The fill solution used: Vt=Vv+Vs
solve for Vv=(0.787)*101261 = 78,984
Vt= 101,261 + 78,984 = 180,245 CY
Now what I did was use the same (e=(Vt/Vs) - 1) formula again, but that gives you the wrong answer (gives Vt = 110,000 CY)
Can anyone enlighten me as to why I would need to use the Vt=Vv+Vs formula (2 steps) versus the other one????????????