ARLORD
Well-known member
In the AISC Seismic Provisions-341-05, pages 3-66 to 3-69,Example 3.11 SCBF Brace-to-Beam/Column Connection Design, they are using the amplified building code loads and not the expected yield load. Where in the specification does it indicate to use amplified loads for SCBF connection design.
For OCBF, section 14.4 clearly indicates when to use the amplified loads, but I do not see a similar indication in Section 13 for SCBF.
Also, in Example 3.12, pg 3-96, Rub=4.9k, from building code Load Combination, not the expected yield load.
Why was amplified loads used in Examples 3.11 and 3.12, and not the expected yield load per section 13.3.
For OCBF, section 14.4 clearly indicates when to use the amplified loads, but I do not see a similar indication in Section 13 for SCBF.
Also, in Example 3.12, pg 3-96, Rub=4.9k, from building code Load Combination, not the expected yield load.
Why was amplified loads used in Examples 3.11 and 3.12, and not the expected yield load per section 13.3.