You are assigned to be the project manager of a 20-story concrete building. The concrete structures from the second level to the top level are consistent. The construction schedule plans for one floor slab concrete pour per week. You need to estimate how many steel jacks it would need to support the floor slabs after formworks are removed. The dimension of the slabs is 88 ft by 106 ft. Spacing of the jacks supporting the slab is 10 ft or less and from edge to edge of the slab. The jacks supporting a floor slab can be removed if the concrete of that floor slab achieve 90 percent of the design strength or more. How many jacks in total do you need approximately?
A/ 120
B/ 500
C/ 400
D/ 200
A/ 120
B/ 500
C/ 400
D/ 200