Caseyuconn
Member
- Joined
- Sep 19, 2010
- Messages
- 11
- Reaction score
- 0
CERM Practice Problems - Intersection Design
I am working on problem located on page 73-3, problem number 4 of the CERM Practice Problems book. It is an intersection design problem. When looking at the solution the effective green is described as " Since the lost time includes the amber time, the effective green is the actual green time."
My question is shouldn't this be g = G + Y + AR - tl? I would think lost time due to start up from green (usually 2 secs) should be the minimum tl.
Any insight would be appreciated.
Thank you
I am working on problem located on page 73-3, problem number 4 of the CERM Practice Problems book. It is an intersection design problem. When looking at the solution the effective green is described as " Since the lost time includes the amber time, the effective green is the actual green time."
My question is shouldn't this be g = G + Y + AR - tl? I would think lost time due to start up from green (usually 2 secs) should be the minimum tl.
Any insight would be appreciated.
Thank you